Phase 1 & 2 (VISTA) Multi-Building Masonry & Plaster Self Storage Facility Value: $5.7 Million Date: December 2001 Client: Nicol Investment Company Architect: Valli Architectural Group
Challenge: This project was built is in two phases because of Client concern about product absorption. In addition, this Developer was interested in keeping phasing costs to a minimum.
Notable Fact: Pacific Construction Group came up with a phasing plan that allowed for completion of the Phase II foundation and slab work that would require a minimum amount of retrofit work for the Phase II building. In addition, the Developer was able to utilize this phase II area for RV parking in the short term.
|
|
|